A24: Site Fill and Compacting Subbase

Go to project master  | Show all progress reports...  | Show similar reports (6) | 

 

Project Reporting by nicaragua365.com

Making sure your construction project in Nicaragua has a happy ending.

Report date: Sunday, October 16, 2011

A24: Site Fill and Compacting Subbase

October Rains

Bad weather this week has hampered progress. Workers haven't been able to arrive and the ground has been too wet to use heavy machinery. Some fill has been delivered & compacted.

Project updates for Construction of a 720 Square Meter Beachfront House at Playa Colorado Surf Break

A24: Cupola Rebar and Roof Frame 3

Cupola form is complete and cupola rebar work underway. First floor water tubing getting connected to ground floor. Ground floor being refilled & compacted ready for concreting.

A24: Cupola Form and Roof Frame 2

Work continues with the roof frame, stuccoing walls, running electric cabling and water pipes. Slab done for star deck. Form made for cupola dome.

A24: Roof Structure and Stuccoing

Steel roof frame going up over ground floor. First floor walls nearing full height. Walls getting stuccoed.

A24: First Floor Form Removed

Formwork used to support the first floor slab has been removed.

A24: First Floor Slab Poured and Walls Going Up

First floor slab poured and work now progressing with the upstairs walls. Stairs also poured. Work is advancing with the domestic water circuit.

A24: Concrete Rebar Spiral Staircase 2

Rebar bent and laid for spiral staircase. Double reinforced grid complete. Ready to pour slab.

A24: Concrete Rebar Spiral Staircase

Form in place for concrete rebar spiral staircase. Double layer of reinforcement going down for first floor slab.

A24: Preparing Formwork for First Floor Slab

Work moving along quickly getting form in place for first floor slab.

A24: Preparing First Floor Rebar

First floor rebar preparations continue and work underway getting the form in place for pouring first floor slab.

A24: Preparring For Second Floor

All walls up to first floor height. Preparing form for second floor and front balcony.

A24: Walls up to First Floor Height

Most walls are up to full first floor height, electrical sockets/ switches being positioned.

A24: Walls Going Up

Most foundations and footings under concrete, work started on walls.

A24: First Blocks Laid

Most foundation trenches and footings dug. First blocks being laid.

A24: Erecting Rebar, Pouring Footings

Rebar structure going up, foundations and footings being concreted in.

A24: Rebar, Footings and Foundations Trenches

Piles of rebar have been prepared and work is well advanced with the footing excavations and foundation trenches.

A24: Breaking Ground, Digging Footings

Grid layed out and ground broken. Manually digging footings.

A24: Preparing Building Grid

Service quarters pad raised to the same level as the main house pad. Driveway prepared with compacted sub-grade. Building grid being prepared prior to starting work excavating foundation trenches & footings.

A24: Building Pad Complete, Bending Rebar

Building pad is complete, bending rebar continues

A24: Raising Level, Preparing Rebar

The heavy rains have passed and work has resumed. The level of the building pad is been raised with heavy grade compacted rubble. Steel rebar is being prepared.

A24: Site Fill and Compacting Subbase

Bad weather this week has hampered progress. Workers haven't been able to arrive and the ground has been too wet to use heavy machinery. Some fill has been delivered & compacted.

A24: Clearing Lot and Preparing Terrace

The lot has been cleared where necessary and work is underway excavating sand to prepare a compacted rubble & subbase building pad.

 