G11: Project Complete

Go to project master  | Show all progress reports...  | Show similar reports (10) | 

 

Project Reporting by nicaragua365.com

Making sure your construction project in Nicaragua has a happy ending.

Report date: Friday, October 07, 2011

G11: Project Complete

Project Complete

The project was finished a few months ago, but the curtains only went up last week. So here are the photos of the completed work.

Project updates for Construction of a 3000 Square Foot Fairway House in Hacienda Iguana

G11: Project Complete

The project was finished a few months ago, but the curtains only went up last week. So here are the photos of the completed, furnished home.

G11: Septic Tanks Installation

Base coat of paint applied to main house. Kitchen and bathroom cabinets fully assembled, including marble counter tops. Swimming pool nearly ready. Lights and fans being hung. Septic tanks.

G11: Swimming Pool Concrete Work Almost Finished

The rough concrete work for the swimming pool is almost finished. The main house kitchen & bathroom cabinets are being installed, just waiting for the granite counter tops.

G11: Windows Installed, Swimming Pool Resized

Most aluminium framed windows installed. Doors, kitchen & bathroom cabinetry on-site and getting installed. Swimming pool resized.

G11: Windows Delivered, Sala Machimbre Complete

A truck load of windows arrived from Guatemala this morning with no breakages. The living room machimbre is complete. Floor tiles have run out.

G11: Swimming Pool Formwork

Concrete base for swimming pool has been poured, steel rebar frame set in place and most of the pine and ply-board form is up. Front terrace fully tiled.

G11: Tiling Floors and Bathroom, Insulating Roof

First air conditioning units installed in main house bedrooms. Insulation being installed above gypsum board in bedrooms. Excavation dug and prepared for swimming pool.

G11: Tiling Floors, Bathrooms, Machimbre Roof

Floor and bathroom tiling underway in the main house. Machimbre wood panelling going up in sala.

G11: Fine Parge, Tiling Roof, Electric Wiring

Walls in the main house are being fine parged. Electrical cabling being run through PVC tubing back to main circuit panel. Roof being tiled.

G11: Main House Roof, Concrete Water Tank

Hoisting main house roof timbers into position. Bamboo work underway over terraces. Concrete water tank finished.

G11: Base Coat of Pain on Service Qts, Timber Roof

Roof timbers still going up in the main house. Sheet rock partition walls finished and base coat of paint applied in the service quarters.

G11: Shower and Floor Tiling in Service House

Most roof timbers prepared, ridge beam hoisted into position in the main house. Service quarters floor and shower tiling complete.

G11: Sheet Rock Partition Walls in Guest House

Service quarters - sheet rock wall partitions being built and floor tiling started. Main house - fine parge finished and roof timber preparations continue.

G11: Main House Roof Timbers, Concrete Floors

Fine parge complete in service quarters. Rough parge still in progress in the main house. Concrete floors going down & timber roof beams going up in main house.

G11: Fine Parge Coat on Srvs Qts, Timber Prep

The service quarters are almost ready for painting. Parging continues on the rest of the house. Timber being prepared for roof beams.

G-11 Parging Walls, Service Quarters

Grey work for the service quarters is being finished off. Main house walls being parged. Timbers being prepared for main house roof.

G-11 Parging Walls, Roof on Service Quarters

The roof is on the service quarters and work is underway parging the walls for the main house. Roof timbers are being prepared for the main house roof.

G-11 Service Quarters Timber and Steel Frame Roof

Timber and steel frame roof going up over the service quarters. The terrace section uses a timber frame, while a metal frame is being used for the roof over the inside area.

G-11 Service Quarters Roof and Floor

Concrete has been poured for the floor of the service quarters. Final bits of block work being finished off in the main house.

G-11 Work Started on Steel Roof Frame

The final bit of block work is getting finished off above the lintels, the forms for the terrace arches are being removed, work has started on steel frame for roof.

G-11 All Walls Up, Pool Terrace Formwork and Fill

All the walls are up to full height. Formwork is up and has been filled for the pool side terrace arches.

G-11 Most Walls and Lintels Up

The majority of the walls are up to their full height and most lintels are done. Some interesting formwork going on in preparation for the archways on the pool side terrace.

G-11 Main Sewer Lines, Arched Lintels

Arched lintels are being constructed over many internal doorways, and at the service quarters terrace. The main sewer line (PVC) is being laid.

G-11 Walls, PVC Electrical Conduits

Some walls are now reaching their full height. PVC electrical conduits getting embedded in concrete walls. PVC water pipes on site.

G-11 Walls Going Up, Block work

Service quarters walls almost finished. A lot of progress has been made on the main house walls over the past 10 days.

G-11 Rebar Foundations, Structure and Walls

Work progresses on the steel rebar foundations & structure. The first walls for the main house are now in process. The service quarters square pillars are being replaced with round ones.

Spread Footings on Compacted Subbase

The walls are starting to go up for the main house. The foundation trenches are still being dug and almost complete. Service quarters block work almost complete.

Foundations Going Down, Walls Going Up...

Site is cleared, filled and compacted. Trenches have been dug for foundations.

 

Get in contact with nicaragua365.com for more details