Most walls are up to full first floor height, electrical sockets/ switches being positioned.
Most foundations and footings under concrete, work started on walls.
Most foundation trenches and footings dug. First blocks being laid.
Rebar structure going up, foundations and footings being concreted in.
Piles of rebar have been prepared and work is well advanced with the footing excavations and foundation trenches.
Grid layed out and ground broken. Manually digging footings.
Service quarters pad raised to the same level as the main house pad. Driveway prepared with compacted sub-grade. Building grid being prepared prior to starting work excavating foundation trenches & footings.
Building pad is complete, bending rebar continues
The heavy rains have passed and work has resumed. The level of the building pad is been raised with heavy grade compacted rubble. Steel rebar is being prepared.
Bad weather this week has hampered progress. Workers haven't been able to arrive and the ground has been too wet to use heavy machinery. Some fill has been delivered & compacted.
The lot has been cleared where necessary and work is underway excavating sand to prepare a compacted rubble & subbase building pad.
The replacement window panes finally arrived and have been installed. The house has been cleaned top to bottom and painting of ceilings has started. All cabinets installed.
All sliding doors/windows, interior doors and cabinets are installed. Interior of guest house painted, likewise ceilings in main house.
The project was finished a few months ago, but the curtains only went up last week. So here are the photos of the completed, furnished home.
All windows now installed, just waiting for replacements from breakages to arrive. Kitchen bar built. Site generally cleared up. The light at the end of the tunnel is blurring into view...
Double glazed Krombeplast windows arrive all the way from sunny Vladivostok via Guatemala and Casa Nova, Managua. Installation almost complete 5 days after delivery.
Just a few profiles remain to be installed and more than half the panes are now in. Corner mitered floor to ceiling windows in upstairs bedrooms. Mosquito screens due to arrive this week. Driveway area taking shape.
Steel rebar and form work complete for the swimming pool and swimming pool light in position. Work has begun pouring concrete for swimming pool walls.
Most small and medium sized window profiles installed and some panes are in. Floor tracks cut and ready for large window profiles. Kitchen marble counter tops and cabinets almost ready.
Swimming pool rebar for base and steps done, just the walls now remain. Gypsum PermaBase walls for internal and external closets, including surf board closet.
Assembling window frames and cutting tracks in tiled concrete floors to reduce height of the base profile above surrounding floor. Steel rails painted.
Shipment of double glazed Aluver windows arrived from Guatemala. Roof on service quarters/ garage. Cabinet installation continues. Steel railings going up.
Base concrete has been poured into swimming pool excavation and work is underway preparing rebar. Floor and bathroom tiling almost complete.
Cabinets getting assembled & installed. Interior doors being hung. Garage block work finished and timber roof structure going up.
Ceramic floor tiles going down in living areas and bathrooms. Connecting up water cistern to external supply. Cover on fourth tank of septic system.
Walls are up for the service quarters and garage. Cabinets and doors have been delivered but not yet installed. Photos of roof top.
Excavation has been dug for the swimming pool and a delivery of steel on-site. Floor tiling has begun on the front terrace. Master bathroom being tiled with the same tile.
All the walls are primed, all ceilings skimmed and primed. Blockwork for retaining wall almost finished. Trench dug in front of house for tidal defence barrier.
Tiling underway on main house roof and plastic guttering up above front & rear terraces. Steel roof girders being clad in decorative wood. Main house walls being primed.
Base coat of paint applied to main house. Kitchen and bathroom cabinets fully assembled, including marble counter tops. Swimming pool nearly ready. Lights and fans being hung. Septic tanks.